Texas’ grid operator is creating a brand new course of to judge a number of large-load interconnection requests on the similar time. The query for cryptocurrency miners and knowledge middle builders which are already in line is: who will get to go first?
That ought to hopefully be sorted out by month’s finish. That’s when the Electrical Reliability Council of Texas (ERCOT) hopes to have standards introduced for which energy-intensive initiatives may very well be thought-about for “Batch Zero,” the primary group to undergo ERCOT’s revised planning course of.
At a Public Utility Fee of Texas (PUC) assembly on Thursday, Jeff Billo, ERCOT’s vice chairman of interconnection and grid evaluation, stated that for “Batch Zero,” the grid operator will take into account proposed massive load interconnection requests from initiatives which were within the queue for a while and don’t have to be restudied. Tasks which are much less far alongside will likely be studied in a later batch, Billo stated.
These requests primarily come from knowledge facilities, crypto mines, industrial websites and hydrogen initiatives. Billo additionally stated that simply because some present initiatives in ERCOT’s queue may warrant one other transmission examine doesn’t imply they couldn’t nonetheless be thought-about for “Batch Zero.”
“There are loads of particulars to fill on the market,” Billo stated. “We’re nonetheless actually early within the technique of designing how that batch examine would work.”
The timing of a transmission examine issues tremendously for firms with billions of {dollars} at stake in developments requiring grid connection. PUC Chairman Thomas Gleeson stated one of many largest factors of competition amongst knowledge middle builders has been uncertainty about the place their initiatives stand, regardless of some having been within the queue for years. Gleeson stated it’s vital to not go away these firms in limbo whereas ERCOT kinds out its new procedures for reviewing a number of requests from massive vitality customers collectively and allocating present transmission capability amongst them. ERCOT beforehand studied massive load customers separately.
“Transparency round that is going to be critically vital to making sure success,” the chairman stated.
The planning round “Batch Zero” comes as ERCOT is nicely into reforming its transmission planning procedures. With the rising variety of massive hundreds searching for to hook up with the grid, ERCOT and utilities can not sustain with the required transmission planning and finish issuing restudies.
The present system, constructed for a big load queue totalling 40 to 50 initiatives, is now slowed down by the 225 new interconnection requests ERCOT acquired final yr, in line with a December report.
Underneath its earlier planning course of, by the point one knowledge middle completed planning research, the outcomes would typically must be reconsidered virtually instantly, as extra initiatives joined the interconnection queue and adjusted the native transmission wants and reliability.
The consensus from early conversations with company stakeholders, together with Google, Meta, CenterPoint, Amazon and OpenAI — all in search of grid capability in Texas—was that the uncertainty within the present course of creates undue threat for builders with present interconnection requests.
The proposed batch technique goals to ameliorate that.
The end result of the brand new course of would decide the variety of megawatts that Texas’ impartial grid might reliably ship and the extra transmission initiatives wanted to allow full interconnection.
If a developer requested a 500-megawatt mission be interconnected in 2028, however the batch examine confirmed that ERCOT might solely reliably present 100 megawatts and would want to endure a transmission improve mission in 2030, the developer can be provided an “on-ramp” of 100 megawatts till the transmission improve is accomplished in 2030, Billo stated for instance. Then, the developer would obtain the complete 500 megawatts of grid energy.
On the finish of the batch examine course of, builders would have a set period of time to make a monetary dedication, Billo stated, to exhibit they’ll proceed with the mission. After that, ERCOT might start a transmission mission to cowl “agency” commitments, which might then be utilized in different batch research.
The preliminary sentiment from “hyperscale” knowledge middle customers like Google, Amazon Net Companies, Meta and Microsoft, builders and impartial energy mills is {that a} batch-based method is critical for big load interconnection, Billo stated.
“Everybody that we’ve got talked to to date has been supportive of us shifting to a batch examine course of,” Billo stated.